Construction progress update of June 2017

(22-09-2017)

On 30 June 2017 we carried out the excavation foundation for T3 building; did fabrication and installation the project's gate also surveyed and marked the building axis.

More Details

Construction progress update of May 2017

(22-09-2017)

After the groundbreaking ceremony, we quickly started focusing on the foundation. On 30/31 May 2017, Vinacco- Contructor of the Project- did pressing pre-casted concrete piles. At the same times, they delivered and unloaded the pre-casted concrete piles. 

More Details

Ground Breaking Ceremony

(21-09-2017)

On date of 11 May 2017 at Quevo Hillview project site, the ground break ceremony has took place with the participation of Board of Directors, core officials and buddhist monk. The activity has officially opened up a new chapter in social housing development in Bắc Ninh. Expectedly, we will

More Details

The Showflat opening event

(21-09-2017)

On 25/26 March 2017 Redamco officially opened the showflat ceremony event with the participation of VIPs and invited guests. The modern and classy design of the showflat has exceeded the guests' expectations. Dozens of apartments have been swiftly reserved. As committed before, Redamco

More Details

Mr Nguyen Tien Nhuong - Bac Ninh People Committee vice chairman visit

(07-10-2016)

On the 13July2016 , Redamco hosted a visit by mr Nguyen Tien Nhuong ( BN PPC vice chairman). Redamco updated him on the progress and status of the issues faced todate.  Mr Nhuong provided some solutions and suggestions

More Details